← All tenders
NCBHydro-MechanicalClosed

Construction of 5 MW Hydroelectric Project Headworks & Intake

KHP/NCB/001/082-83

Bid Security
NPR 30,00,000
Estimated Cost
NPR 14,85,00,000
Bid Validity
90 days
Deadline
18 Sept 2026, 15:16

Procurement Schedule

Pre-bid Meeting
08 Sept 2026, 03:18
Technical Opening
18 Sept 2026, 17:18
Financial Opening
20 Sept 2026, 17:20

Scope & Description

Arc and Civ Hydro invites eligible and qualified contractors to submit bids for the construction of the headworks and intake facilities of a 5 MW run-of-river hydroelectric project in Nepal. The scope of works includes site preparation, temporary access and diversion works, river training and protection works, intake structure, approach channel, desanding arrangements, concrete and reinforced-concrete works, foundations, retaining and protection structures, drainage, embedded items, mechanical and electrical interfaces, installation of gates and associated components, testing, commissioning support, site restoration, and all ancillary works necessary for completion of the facilities. The successful contractor shall provide all required labour, supervision, construction equipment, materials, temporary works, transportation, testing, quality control, health and safety measures, environmental protection measures, and other resources necessary to complete the works in accordance with the approved drawings, technical specifications, BoQ, applicable standards, and contract conditions.

Tender Documents

Submit Your Bid

Sealed two-envelope submission. Your financial proposal stays encrypted and unopened until the scheduled financial opening. All submissions are audit-logged.

This tender is currently under evaluation.

ProjectDarbang Myagdi Hydro-Electric Project
Drawing No.DKHL-DMHEP-001
Status[ Under Construction ]
Darbang Hydro Logo
© 2026 DHAULAGIRI KALIKA HYDRO LIMITED // ALL RIGHTS RESERVED.
PRIVACYTERMS[ SYSTEM DESIGN: ADVAITA ]